Room for the River | Nijmegen, The Netherlands | H+N+S Landscape Architects

© Siebe Swart

The Netherlands forms the low-lying delta of North-Western Europe. Over the past 1000 years the rivers have been harnessed between higher and stronger dikes. However, due to climate change, river discharges have increased and extreme high water levels are expected to occur more frequently. After the river flooding in 1995, the national Room for the River programme was initiated to give back more space to the rivers in order to reduce the risk of flooding.

Before
After

The goal of the Dutch Room for the River Programme is to give the rivers more room, to be able to safely process higher water levels. At more than 30 locations, measures are taken to give the river space to reduce flood risks. The measures are designed to improve the quality of the immediate surroundings.

Before – High Water Level ©RWS

This is the most complex project within the Room for the River programme. By constructing a bypass channel, an elongated island is created in the river Waal, between the historic centre and the north shore of the Waal River. Several new bridges improve the connectivity of the area. The island and bypass channel together form a river park that not only reduces flood risks, but also offers recreational, ecological and aesthetic values.

The river park forms the highlight of Nijmegen’s new flood protection for the Waal River. The design is based on the river water dynamics, the erosion and sedimentation process and the tides. The Urban River Park is freely accessible and respectfully integrates archaeological and historical elements into the design. The innovative park design enables the space to be utilised in different ways, including the hosting of events and exhibitions on the new island.

© Johan Roerink

The plan consists of three elements: creating, growing and water movement. The layer ‘creating’ represents the physical elements that are built, constructed, dug or raised in the construction phase. The second layer, ‘growing’, shows how the landscape may develop in the future (natural and built environment). The third layer, ‘water movement’, shows the fluctuation of the water levels throughout the seasons.

First Winter
First Summer

Experiencing the river landscape and incorporating the river dynamics was one of the main objectives in our design. Some paths will occasionally be flooded in the event of high water levels, only being accessible via stepping stones. Also the accessibility of the river has been improved. Furthermore, conditions for sedimentation and erosion processes are carefully included in the design, which will gradually create various ecotypes, characteristic for the river landscape.

© Siebe Swart
© Siebe Swart

Room for the River | Nijmegen, The Netherlands | H+N+S Landscape Architects

Team
H+N+S Landscape Architects (coordinating architect & landscape design)
Dura Vermeer / Ploegam (contractors)
- Zwarts & Jansma Architects / Ney-Poulissen Architects & Engineers / NEXT Architects (bridge architects)
Trafique (landscapes architect)

Project duration | 2012-2016
Location | Nijmegen-Lent, The Netherlands
Surface area: 120 ha flood plain
Total costs | € 126,000,000,
Client | Nijmegen Municipality & project office Room for the River

Images | H+N+S Landscape Architects (unless noted)

About Damian Holmes 3276 Articles
Damian Holmes is the Founder and Editor of World Landscape Architecture (WLA). He is a registered landscape architect (AILA) working in international design practice in Australia. Damian founded WLA in 2007 to provide a website for landscape architects written by landscape architects. Connect on Linkedin at https://www.linkedin.com/in/damianholmes/